Case study
Below-Ground Oil-Water Separator for a Military Base
A 300 GPM double-wall separator configured for deep burial and traffic-rated access.

Executive Summary
A military base in South Carolina needed a below-ground oil-water separator for stormwater and industrial runoff. Over a 17-month engineering and procurement cycle, Ecologix worked with the general contractor and site-work subcontractor to refine the specification and configure a 300 GPM, 3,000-gallon double-wall separator. The project architect approved the equipment submittal, and Ecologix released the unit to fabrication.
The Challenge
The planned tank capacity shifted from 3,000 to 5,000 gallons during design before returning to 3,000 gallons. The final design also called for nine-foot manway extensions to reach finished grade and H-20 traffic-rated covers. By the time procurement passed from the general contractor to the site-work subcontractor, earlier drawings, pricing and commitments needed to carry forward into the formal submittal.
The Engineered Solution
Ecologix configured a model HQB-3064 below-ground oil-water separator with a double-wall tank and integrated monitoring. The removable coalescing media was specified to separate free, non-emulsified oil under laminar flow conditions.
| Specification | Project configuration |
|---|---|
| Design flow rate | 300 gallons per minute (GPM) |
| Capacity | 3,000 gallons total, including 2,400 gallons of oil spill capacity |
| Tank construction | Double-wall carbon steel specified to UL 58 and UL 1746, with 100-mil exterior FRP corrosion protection and an internal coal-tar epoxy coating |
| Coalescing media | 36 ft³ of removable HD Q-Pac parallel corrugated polypropylene media |
| Monitoring | Integrated oil-level monitoring and interstitial leak detection |
| Access and anchoring | Two nine-foot manway extensions, hold-down anchor straps and provisions for H-20 traffic-rated covers and rings |
From Contractor Handoff to Fabrication
Ecologix gave the site-work subcontractor updated pricing and the earlier technical commitments. It confirmed the manway extension scope and itemized traffic-rated covers by access point, giving the subcontractor the option to source them locally. One control panel handled both oil-level monitoring and leak detection, avoiding a second panel.
The subcontractor arranged upfront billing with the general contractor to fund the custom steel order. Ecologix provided general arrangement drawings, burial-depth information and control panel data for the architect’s review. After submittal approval, Ecologix released the unit to the planned 12- to 14-week fabrication queue.
Project Outcomes
- The architect approved the submittal for the final tank, access and monitoring configuration.
- Updated tank and anchor-strap pricing helped offset the cost of added traffic-rated accessories.
- Procurement and payment coordination kept the release to fabrication on schedule.
Designing a below-ground oil-water separator system?
Share your design flow, spill capacity, burial depth and surface loading requirements with the Ecologix team.
Request Assistance